E-Letter responses to:
-
- letters:
Joseph F. DeCarolis, David W. Keith, Mark Z. Jacobson, and Gilbert M. Masters
- The Real Cost of Wind Energy
Science 2001; 294: 1000-1003
[Full text]
|
|
Published E-Letter responses:
-
Response to letter by Howard Gruenspecht of November 21, 2001
- Mark Z. Jacobson and Gilbert M. Masters
(28 November 2001)
-
Response to DeCarolis and Keith response of November 21, 2001
- Mark Z. Jacobson and Gilbert M. Masters
(28 November 2001)
-
Response to Alfred Cavallo letter of November 21, 2001
- Mark Z. Jacobson and Gilbert M. Masters
(28 November 2001)
-
Re: Re: Wind vs. Coal
- Howard Gruenspecht
(21 November 2001)
-
Response to Jacobson and Masters
- Joseph F. DeCarolis and David W. Keith
(21 November 2001)
-
Re: Re: Wind vs. Coal
- Alfred Cavallo
(21 November 2001)
-
Re: Wind vs. Coal
- Mark Jacobson and Gilbert Masters
(14 November 2001)
-
Wind vs. Coal
- Dan S. Golomb
(14 November 2001)
-
Don't Dismiss the Midwest's Power Needs
- Dr. Josh Kurutz
(2 November 2001)
|
Response to letter by Howard Gruenspecht of November 21, 2001 |
28 November 2001 |
|
|
Mark Z. Jacobson and Gilbert M. Masters, Associate Professor (MZJ); Professor (GMM) Department of Civil and Environmental Engineering, Stanford University
Respond to this E-Letter:
Re: Response to letter by Howard Gruenspecht of November 21, 2001
|
We thank Gruenspecht for his comments. We will
address them, below.
First, Gruenspecht makes the same point as DeCarolis
and Keith, that when wind is a large fraction of the
energy production, more backup energy may be
needed. We addressed the issue in detail in our
Response 2 to DeCarolis and Keith's response of
21 November 2001, so we do not repeat it here.
Second, Gruenspecht says that 10,000 km provides only 30
km of transmission per gigawatt of wind capacity. This
statement is incorrect. One transmission line can
transmit 2 GW of actual power = installed GW / capacity
factor. For a CF of 0.36, this translates to an installed
power of 5.5 GW. Thus, for 225,000 1.5-MW turbines,
about 61 lines are needed, and 10,000 km / 61 lines =
163 km/line. As such, for transmission to cost <1% of
direct wind cost, the average transmission line for
225,000 turbines can be up to 163 km. This number
may be reduced to around 100 km/line to account for
overlapping transmission during times when wind is
peaking and for other factors. The 100 km/line is
consistent with a number derived independently in our
response to Cavallo's 21 November 2001 letter, which
is based on an earlier analysis by Cavallo, who
accounted for overlapping. Even if 50,000 km of
transmission lines are required (500 km/line) the net
cost is still <5% the direct cost of wind energy (3 to 4
cents/kWh) and <1.5% the price a typical consumer
pays for electricity, which is 11 cents/kWh.
In addition, we disagree with the implication that the
Siemens et al. bid of $5 billion for transmission lines
out of a $15 billion project means that transmission is
one-third the cost of wind energy. The transmission
lines will have lifetimes of 40 to 60 years; the wind
turbines, 20 years. The $5 billion investment in
transmission lines will survive two to three generations
of turbines. In addition, this example applies only if the
transmission lines are long, which is not always
necessary.
Third, Gruenspecht statement that even old coal-fired
plants produce electricity at 1 to 1.5 cents per kWh direct
cost appears low. Their costs are often cited as 2 to 3
cents/kWh. Regardless, the direct cost is not the cost to
the U.S. citizen. The cost to the U.S. citizen is the total
cost: the direct + health/environmental + subsidy cost.
The health/environmental costs of old coal power
plants exceed those of new coal power plants, and both
far exceed the total cost of wind. Thus, our conclusion
that the direct+health/environmental cost of wind is less
than that of coal (whether old or new) still stands, and
this is the only cost comparison that matters from a
public policy point of view.
Fourth, Gruenspecht correctly states that most new capacity
is natural gas. The direct cost of a new natural gas
power plant is 3.3 to 3.6 cents/kWh (Office of Fossil
Energy, 2001). Natural gas emits carbon dioxide,
methane, carbon monoxide, nitrogen oxides, particulate
matter, reactive organic gases, ammonia, and other
pollutants that exacerbate global warming, urban
smog, particulate health problems, acid deposition,
and visibility degradation. We calculate a tentative,
conservative global warming cost of natural gas as
0.7 to 1.1 cents/kWh and other health/environmental cost
as 0.5 to 1.1 cents/kWh, which gives the
direct+health/environmental cost of natural gas as
4.5 to 5.8 cents/kWh, more expensive to society than wind
(3 to 4 cents/kWh) but less expensive than coal (5.5 to 8.3
cents/kWh). As such, we believe our conclusions apply
to both coal and natural gas.
Fifth, Gruenspecht states that most black lung cases
reflect past, not current, mining practices, and the
number of black-lung deaths would not be appreciably
impacted by the prospective reduction in coal use. This argument glosses over a real problem and
misrepresents our point. First, the federal government still pays hundreds of
millions of dollars per year in black lung subsidies, and
miners in the U.S. still contract black lung disease by
working in coal mines today. Miners, globally, contract
black lung disease at higher rates. Second, the cumulative federal black-lung payments,
brought to present value, are around $70 billion. The
cumulative subsidy has allowed coal to gain an
advantage in pricing and lobbying, and this advantage
has, in turn, resulted in greater pollution output. For
wind to obtain a level playing field, we argue that the
federal government should spend the same $70 billion
by purchasing wind turbines (or that coal should pay
back the $70 billion). This amount alone would allow
the replacement of 10% of coal with wind. Unlike with
the black lung subsidy, the government could recoup its
entire investment if it purchased turbines and sold the
electricity.
References and Notes
Office of Fossil Energy, Department of Energy; see
http://fossil.energy.gov/coal_power/special_rpts/market
_systems/market_sys.html, 2001. |
|
Response to DeCarolis and Keith response of November 21, 2001 |
28 November 2001 |
|
|
Mark Z. Jacobson and Gilbert M. Masters, Associate Professor (MZJ); Professor (GMM) Department of Civil and Environmental Engineering, Stanford University
Respond to this E-Letter:
Re: Response to DeCarolis and Keith response of November 21, 2001
|
We thank DeCarolis and Keith for their important
comments and for furthering this debate. We believe
that we have reached convergence on several issues
and that some issues will not be completely resolved at
this time. On other issues, though, we still respectfully
disagree, and we believe that the conclusions of our
original paper still hold. Below are responses to
DeCarolis and Keith's points in their response of
21 November 2001, in the order they are given.
(Point 1) Hirst's (2001) analysis addressed one aspect of
intermittency, the cost of regulation ancillary service. He
found the cost to be small (0.005 to 0.03 cents/kWh,
less than 1% of the direct cost of wind energy). A
similar study was performed by Hudson et al. (2001)
who also found that the cost of regulation ancillary
service to be small when wind is integrated into a grid
(0.006 cents/kWh).
(Point 2) As DeCarolis and Keith correctly point out, there is a second issue related to intermittency, and this is the
potential cost of supplying backup energy when wind
becomes a large fraction (e.g., 30%) of energy supply
and wind's output is low for a given hour. The real
question here, though, is not what is the cost to wind, if
any, in this case, but what is the difference between the
cost to wind and the cost to coal or natural gas (since
we did not account for this potential cost with respect to
either coal, natural gas, or wind in our paper).
We suggest that the cost to wind due to backup
reserves could be less than or more than that to natural
gas and coal and the net cost, either way, is uncertain.
As such, we believe it is incorrect to presume a cost or
a benefit as DeCarolis and Keith have done. Before the
work of Hirst and Hudson et al., it was commonly
presumed that wind had a high cost of regulation
ancillary service. This assumption turned out to be
incorrect. Similarly, it should not be presumed that
expansion of wind energy will result in a higher cost of
contingency reserves than the current cost. The main
reasons we believe the net difference in contingency
reserve costs could be either negative or positive are
given as follows.
First, backup sources of power are already in place and
are used when natural gas or coal power plants fail,
supplies tighten, or energy demand increases beyond
expectations suddenly. The forced outage rate for all
fossil fuel power plants is, on average, 8% (North
American Electric Reliability Council, 2000). This
compares with a failure rate for modern wind turbines
of 2% (Danish Windpower Manufacturers
Association, 2001). As such, if wind displaces coal, the
reliability rate of replaced energy, in terms of energy
source failure alone, will improve immediately by 6%. DeCarolis and Keith use in their example a
peak load of 52 GW. If 30% of 52 GW is supplied by
replacing coal with wind, backup requirements for
failure will be reduced by 1 GW. Replacing natural gas
with wind will result in a proportional reduction.
Second, whereas wind is an intermittent energy source,
natural gas is also an intermittent energy source. This
is evidenced by the variations in natural gas prices of
50 to 100% from month to month and year to year
(e.g., McFeat, 2001). This price variation is caused in
large part by a variation in natural gas supply. The
variability of natural gas supplies and prices suggests
that, if wind replaces natural gas, backup requirements
may not change much.
Third, peaker plants are used commonly today when
energy demand exceeds expectations. Thus, a certain
amount of backup is already necessary, regardless of
the energy source.
Fourth, there are several ways to provide backup
energy. Some include increasing hydroelectric output,
transmitting from outside the grid, using peaker plants
(usually fossil fuel), and storage.
(i) Hydroelectric power supplies 10% of energy in the
United States (only 4% outside of California, Oregon, and
Washington). When hydroelectric output is increased
as a backup, there is little additional cost.
(ii) If wind becomes 30% of the energy supply,
wind farms will be distributed over greater areas, and
grid interconnections will expand, enabling easier
transmission of excess wind, solar, hydroelectric, and
fossil energy from outside the local grid, thereby
reducing and potentially eliminating the need for peaker
plants for backup. In other words, the expansion of wind
energy may reduce the cost of backup energy by
enlarging the size of a grid and by facilitating
transmission of excess wind and other types of energy
from outside the grid when needed.
(iii) A large future energy requirement may be to
generate hydrogen for fuel cells. In such a case,
intermittency is no longer an issue, and only total
energy output over a year is. Wind is reliable for
producing an aggregate amount of energy over a period
of a month to a year.
(Point 3)(i) Whereas we agree that the Great Plains contains
the largest concentration of ideal wind sites, there are
plenty of land and water sites with equal or greater wind
power that have still not been exploited. The fastest
wind sites in the country (>9.4 m/s on average) are all
along the coast, such as of North Carolina, South
Carolina, and and Louisiana (Archer and Jacobson,
2001, first figure - please note that the figure gives
speeds at the measurement locations only). Sites exist
in numerous states that are very fast.
(ii) For a distance of 2000 km, we estimate the cost of
new HVDC lines as about 0.7 cents/kWh (see
footnote), which is about half the average value given by
DeCarolis and Keith (although the uncertainty is within
the margin of error of their estimate). However, we
disagree with their assumption that most lines need to
be 2000 km. A total of 840,000 MW of wind power lie within 20
km of existing transmission lines. Our proposal
requires the generation of only 128,000 MW of power
(225,000 1.5 MW turbines in the presence of 7 to 7.5 m/s
winds, giving capacity factors of 0.35 to 0.4). A reasonable
portion of our required power can be obtained from
turbines close to existing transmission lines. If such
lines are already saturated with power, the cost of
additional lines is not a cost of wind exclusively but a
shared cost among all energy sources using the lines,
because coal and natural gas generally do not own such
lines, and therefore, do not have an exclusive right to
them.
(iii) Siting almost all turbines in the Great Plains would at first glance make sense, but the larger the area that
turbines are distributed over, the higher the minimum
power output summed over all turbines (please see
Archer and Jacobson, 2001) and the lesser the
contingent backup energy required to account for a
worst-case scenario for wind. In other words, if all
turbines are placed in one region, a high pressure
system could cause slow winds in that region. If
turbines are placed in many areas of the country, the
chances are slim that all regions will have slow winds
at the same time.
In addition, our speculation is that most development
will ultimately occur offshore, since offshore area is
essentially unlimited, most people live near the coast,
winds are generally faster over water than land, winds
are very regular and predictable near the coast,
turbines can be placed far enough out that people don't
see them, and new turbines cause minimal
environmental damage (the large, slow-moving
turbines do not cause bird loss any more).
(Point 4) DeCarolis and Keith say, "...but to assert that the
cost of wind energy is low less that of coal is not
accurate. If it were, we would expect to see wind
dominate virtually all new capacity installations (given
the 1.5 cents/kWh tax incentives), rather than simply
having the fastest relative growth rate..."
First, our paper compared the direct cost of new
coal with that of new wind, not the direct cost of old coal
with new wind. We concluded that the direct costs of
new coal and new wind are comparable, in the 3 to 4
cents/kWh range, and this conclusion is supported by
Bolinger and Wiser (2001, p. 3), who calculated the
25-year real costs of 17 wind farm proposals in
California in 2001 as 3.2 to 3.7 cents/kWh, with a
weighted average value of 3.6 cents/kWh. Their
analysis also stated that the numbers were based on
proposal information that presumably contained
worst-case estimates for wind.
Second, why should wind dominate coal or gas in
the marketplace when the direct costs are similar in
both cases. Whereas wind receives a Production Tax
Credit, coal receives a percentage depletion allowance
for mining operations, deductions for mining
exploration and development costs, special capital
gains treatment for coal and iron ore, a special
deduction for mine reclamation and closing, research
subsidies, and black-lung benefits paid for by the
federal government. Oil and gas (mined together)
receive a percentage depletion allowance, a 15%
credit for enhanced oil recovery, a deduction for
intangible drilling and development costs, a "passive
loss" tax shelter for investors in oil and gas, a
nonconventional fuel production credit, and research
subsidies.
Third, the Production Tax Credit for wind can be fully
realized only if the price of wind energy exceeds the
cost of wind energy by 2.5 to 3.75 cents/kWh. As such,
either wind producers benefit only partially from the
credit or the Credit itself drives up the price of wind.
This is easily proven:
In order to fully realize the credit, the price of wind over the cost of wind must be the credit (1.5 cents/kWh)
divided by the marginal tax federal plus state tax rate
(40 to 60%), which gives 2.5 to 3.75 cents/kWh. Thus,
if the cost of wind is 3.5 cents/kWh, the credit will be
fully realized only if the price of wind is 6 to 7.25
cents/kWh (becuase the 3.5 cents/kWh cost is deductible).
Wind producers are likely to optimize by raising their bid
prices sufficiently to take advantage of the credit but not
too high so that their projects are priced out of the
selection. Ironically, then, the credit serves as a
disincentive to reduce the price of wind (which is not the
same as the cost of wind). A direct subsidy would be
better because it would not provide incentive to
maximize the difference between the price and cost of
wind.
Fourth, it is commonly known that it is much easier for large
producers of any product to offer a lower price, thereby
having a smaller profit margin (but a larger net profit
summed over all sales) than it is for a small producer,
who must offer a higher price at a lower sales volume.
Finally, the market for new power plants is not a free
market. In California, for example, separate bids are
requested for renewable energy sources versus fossil
power sources. One reason for the separate treatment
is the misperception (as shown by Hirst and Hudson et
al), that on a small scale, the intermittency of wind
triggers an extra cost.
Footnote: The cost of HVDC lines is calculated as follows:
Cavallo (1995) estimates the cost of transmitted energy
through a 2000-km HVDC transmission line as 2.75
cents/kWh. This translates to 0.00138 cents/kWh/km.
Cavallo assumed a capital charge rate of 0.107, which
translates to an interest rate of 9% over 20 years.
However, transmission lines can last 40 to 60 years.
Further, commercial interest rates today are lower than
9%. These combined factors alone would reduce
Cavallo's estimate by a factor of 2. Cavallo (1995) also
acknowledges that the transmission line cost used
was conservative and "could be about one-half what we
have assumed." Changes in assumptions about
interest rate, transmission line lifetime, and direct costs
would change Cavallo's transmission cost estimate to
0.000345 cents/kWh/km. This estimate could be
reduced further by piggybacking new lines on existing
transmission powers. Nevertheless, the 0.000345
cents/kWh/km cost reaches 1 percent our estimated
direct cost of wind energy (3 to 4 cents/kWh) when the
average transmission line is 88 to 116 km long. Even if
the average transmission line is 500 km long, the cost
is still less than 5% the direct cost of wind. In the worst
case (2000 km line), the cost is around 20% the direct
cost of wind (0.7 cents/kWh).
References and Notes
Archer, C. L., and M. Z. Jacobson, The regularity and
spatial distribution of U.S. windpower,
http://fluid.stanford.edu/~lozej/winds/winds.html, 2001.
Bolinger, M., and R. Wiser, Summary of Power Authority
Letters of Intent for Renewable Energy, Memorandum,
Lawrence Berkeley National Laboratory, October 30,
2001.
Cavallo, A. J., High-capacity factor wind energy
systems, JSEE 117, 137-143, 1995.
Danish Windturbine Manufacturers Association, "21
Frequently Asked Questions About Wind Energy,"
(updated 16 April 2001)
http://www.windpower.dk/faqs.htm, 2001.
Hirst, E., Interactions of wind farms with bulk-power
operations and markets,
http://www.EHirst.com/PDF/WindIntegration.pdf, 2001.
Hudson, R., b. Kirby, and Y.-H. Wan, The impact of wind
generation on system regulation requirements, AWEA
Wind Power 2001 Conference, 2001.
McFeat, T., The unnatural price of natural gas, CBC
News Online,
http://www.cbc.ca/news/indepth/background/gas_hikes.
html, 2001.
North American Electric Reliability Council, Generating
Unit Statistical Brochure, 1995-1999, Princeton, NJ,
October, 2000. |
|
Response to Alfred Cavallo letter of November 21, 2001 |
28 November 2001 |
|
|
Mark Z. Jacobson and Gilbert M. Masters, Associate Professor (MZJ); Professor (GMM) Department of Civil and Environmental Engineering, Stanford University
Respond to this E-Letter:
Re: Response to Alfred Cavallo letter of November 21, 2001
|
We thank Cavallo for his contribution to this debate.
However, we believe his letter misstates the
comparison made in our paper. Second, his
implication that wind power is not cheap relative to
natural gas or coal is contradicted by a third-party
analysis of 17 California wind proposals in 2001 that
supports our conclusion that the direct cost of wind is
3 to 4 cents/kWh. Third, his implication that the Production
Tax Credit reflects the attributes of wind is contradicted
by the stated purpose of the credit. Finally, we believe
his comments about transmission lines are misplaced
and his cost estimates of transmission lines too high.
First, Cavallo implicitly assumes that we compared the
direct cost of new wind with the direct cost of all (old +
new) coal. Instead, our paper compared (i) the direct
cost of new coal with that of new wind, and (ii) the direct
+ health/environmental costs of new or old coal with
those of new wind (since the health/environmental
costs of old coal are higher than those of new coal, the
total cost is likely to be similar in both cases). Nowhere
did we discuss the direct cost of old coal with that of
new wind, nor do we believe this matters from a public
policy point of view. From such a point of view, the only
relevant issue is the total
(direct+health/environmental+subsidy) cost of wind
versus that of coal because whether wind replaces coal
is a political, not a marketplace, decision (regrettably,
we did not discuss coal or wind subsidies in our
original paper). It is not a marketplace decision
because, even when wind and old coal prices are
exactly the same, there is no incentive for coal
producers merely to fold up. Coal producers will fold up
only when government decides to (i) require old and
new coal to eliminate emissions, (ii) require old and
new coal to pay for the health and environmental
damage caused by remaining emissions and mining,
and (iii) reduce the subsidies given to coal in excess of
those given to wind. At the same time, government itself
can promote wind to ensure that new fossil energy
does not take a larger foothold.
Second, we believe our estimated direct cost of energy
from wind (3 to 4 cents/kWh) is correct for the conditions
assumed and is beginning to be reflected in wind
proposals. For example, Bolinger and Wiser (1, p. 3) calculated the 25-year real costs of 17 wind farm
proposals in California in 2001 as 3.2 to 3.7 cents/kWh,
with a weighted average value of 3.6 cents/kWh. Their
analysis also stated that the numbers were based on
proposal information that presumably contained
worst-case estimates for wind.
Third, Cavallo says that "wind power receives
premium payments to reflect its attributes...and indeed
the U.S. Production Tax Credit program does just this."
This is incorrect. The purpose of the tax credit is to level
the playing field in terms of past and current subsidies
that have favored the development of coal and natural
gas technologies and that have kept the price of coal
and gas low. Specifically, the House Ways and Means
Committee stated (H. Rpt. 102-474, Part 6, p. 42),
"The Credit is intended to enhance the development of
technology to utilize the specified renewable energy
sources and to promote competition between
renewable energy sources and conventional energy
sources."
The credit does not address the attribute of renewable
energy, namely, its health, environmental, and climate
benefits over natural gas and coal. It addresses
inequities in past and present subsidies. Even with the
tax credit, tax and current direct government subsidies
to coal and natural gas far exceed those of wind.
Current tax and other subsidies for coal and natural
gas are in the billions of dollars per year
(http://www.foe.org/DLS for starters), whereas
subsidies under the Production Tax Credit are on the
order of $100 million per year.
Fourth, we believe Cavallo's comments about
transmission lines are out of context. He states that
"transmission lines are not only costly, but quite difficult
to site." We agree with these general statements but do
not believe that translates into a high cost per kilowatt hour for
wind energy.
(i) Transmission access pathways already crisscross
the United States, and many already pass through the Great
Plains. If new, long transmission lines are needed for
wind plants, most of these lines can piggyback on
existing transmission towers, and smaller
transmission lines on existing towers can be
upgraded. Adding new lines to existing towers or
replacing existing lines is less expensive than creating
new towers. Only local connections to the nearest
long-distance transmission pathway require siting of
new transmission pathways.
(ii) Whether the high cost of transmission lines per
unit distance translates into a high cost per unit energy
(kWh) depends on the length of the transmission line,
so it is incorrect to label transmission costs as "high"
without specifying the length of the line.
Cavallo (2) estimated the cost of transmitted energy
through a 2000-km HVDC transmission line as 2.75
cents/kWh. This translates to 0.00138 cents/kWh/km.
Cavallo assumed a capital charge rate of 0.107, which
translates to an interest rate of nearly 9% over 20 years.
However, transmission lines can last 40 to 60 years.
Further, commercial interest rates today are lower than
9%. These combined factors alone would reduce
Cavallo's estimate by a factor of 2. Cavallo also
acknowledged that the transmission line cost used
was conservative and "could be about one-half what we
have assumed" (2). Changes in assumptions about
interest rate, transmission line lifetime, and direct costs
would change Cavallo's transmission cost estimate to
0.000345 cents/kWh/km. This estimate could be
reduced further by piggybacking new lines on existing
transmission powers. Nevertheless, the 0.000345
cents/kWh/km cost is 1% of our estimated
direct cost of wind energy (3 to 4 cents/kWh) when the
average transmission line is 88 to 116 km long. Even if
the average transmission line is 500 km long, the cost
is still less than 5% of the direct cost of wind (and <1.5%
the price a typical consumer pays for electricity, which is
11 cents/kWh). In the worst case (2000 km line), the
cost is around 20% of the direct cost of wind (and <6%
the price a consumer today pays for electricity).
We have cited before that 840,000 MW of wind power lie
within 20 km of existing transmission lines. Our
proposal requires the generation of only 128,000 MW of
power (225,000 1.5-MW turbines in the presence of
7 to 7.5 m/s winds, giving capacity factors of 0.35 to 0.4).
Clearly, a reasonable portion of our required power can
be obtained from turbines close to existing
transmission lines. If such lines are already saturated
with power, the cost of additional lines is not a cost of
wind exclusively but a shared cost among all energy
sources using the lines, because coal and natural gas
generally do not own such lines, and therefore, do not
have an exclusive right to them.
In sum, we suggest that higher cost of long
transmission lines is compensated for by lower cost of
shorter transmission lines. If the average transmission
line is less than 100 to 500 km long, the resulting cost of
energy related to transmission lines is less than 1 to 5% of
the price of wind energy.
(c) In his letter, Cavallo says that transmission costs
are high for wind but omits the fact that, when
comparing coal and wind, it is necessary to compare
the transmission costs of both, not merely to state that
wind has a high transmission cost. There are
thousands of coal plants in the United States and tens of
thousands of miles of transmission lines needed to
transmit coal energy. Not only do current transmission
costs exist for coal, but when coal transmission lines
do wear out (and most are fairly old now), they need
replacing.
References and Notes
1. M. Bolinger, R. Wiser, Summary of Power Authority
Letters of Intent for Renewable Energy, Memorandum,
Lawrence Berkeley National Laboratory, 30 October
2001.
2. A. J. Cavallo, High-capacity factor wind energy
systems, JSEE 117, 137 (1995). |
|
Re: Re: Wind vs. Coal |
21 November 2001 |
|
|
Howard Gruenspecht, Resident Scholar Resources for the Future
Respond to this E-Letter:
Re: Re: Re: Wind vs. Coal
|
Letters from DeCarolis and Keith (Science, Nov. 2) and Golomb
(dEbates, Nov 14) argue that the cost of contingency reserves to back up
intermittent wind power omitted from the Jacobson and Masters
proposal(Science, Aug. 24, p. 1438) to substitute wind for coal on a
massive scale is significant. In response, Jacobson and Masters (Nov. 2,
Nov
14) reference a recent paper by Hirst (1), which they say shows that
these costs are trivial. However, the cited paper explicitly states that
its ancillary service cost estimates for integrating wind do not include
contingency reserves. Hirst's rationale for excluding contingency
reserves, that wind farms (typically a fraction of 1 gigawatt (GW)
capacity) do not contribute to the need for reserves required to meet the
largest system contingency
(typically in the range of 1 GW), clearly does not apply to the Jacobson
and Masters proposal to install 321 to 354 GW of wind in the Dakotas.
Where wind variation is the largest system contingency, as it would
be under the Jacobson and Masters proposal, conventional reliability
criteria would require reserves sufficient to meet load under the calmest
1-day-in-10-year wind conditions. With the rapid drop in generation as
wind speed falls below its mean level (according to
references cited by Jacobson and Masters, generation drops to zero at
roughly 3 m/s), required contingency reserves equal to a significant
fraction of the wind capacity envisioned under the Jacobson and Masters
proposal would be needed. Significantly, Golomb notes that average
windspeed in Bismarck is less than 3 m/s 40 percent of the time - a
sobering consideration, given the likelihood of significant correlation in
wind conditions across individual windfarm sites in North Dakota.
DeCarolis and Keith also say that there are likely to be
significant costs of moving power to load centers. In response, Jacobson
and Masters outline a calculation that costs 10,000 km of transmission lines at
$3.1 billion, less than 1% of wind turbine costs. However, 10,000 km
provides only 30 km of transmission per gigawatt of wind capacity added under
their proposal. This could perhaps meet local interconnection and grid
enhancement needs, but not the need for long-distance transmission to load
centers. Existing project proposals provide a firmer basis for
estimating the latter cost. For example, Siemens and Black, and Veatch,
experienced power system engineers and vendors, have recently analyzed a
plan to add 8 GW of capacity in North Dakota and connect it to load
centers in the Chicago and Los Angeles area by HVDC transmission.(2)
Subtracting generating capacity costs from their $15 billion total project
cost estimate suggests a transmission component cost of roughly $5
billion. A system capable of carrying 8 GW from North Dakota to only
one load center would probably cost $3 billion, since two of the three
sets of AC/DC converters would still be needed. Eight gigawatts is only 2 to 2.5
percent of the power that would be moved under the Jacobsen and Masters
proposal, validating the DeCarolis argument that long-distance
transmission costs are more than noise in the overall cost evaluation of
that proposal.
In addition to the foregoing comments related to previous exchanges, Jacobson and Masters' focus in theiroriginal Policy Forum on comparisons between the levelized costs of new
wind and coal plants is something of a red herring because their actual
proposal involves replacing generation from existing coal-fired plants,
which costs 1 to 1.5 cents per kilowatt-hour, with new wind power.
Furthermore,
in cases where new capacity is needed now, the overwhelming choice in
today's markets is for gas-fired units, which are both cheaper and cleaner
than coal, but not even mentioned. Information they provide regarding
black-lung deaths is also misleading in the context of this
article. Most black-lung cases reflect past, not current, mining
practices, and the number of black-lung deaths would not be appreciably
impacted by the prospective reduction in coal use under their proposal.
Competition between coal-fired and wind-powered generation will
likely grow increasingly important over time. Each will have to overcome
fuel-specific hurdles. For wind, these include the costs of contingency
reserves and the need to overcome public objections to siting new
transmission lines and turbines. For coal, these include the costs of
increasingly stringent controls on conventional pollutants and the likely
future requirement to capture and sequester carbon emissions.
Notwithstanding the shortcomings of the Jacobson and Masters analysis,
wind appears well-positioned to provide an important share of
generation capacity additions over the coming decades.
References and Notes
(1) Hirst. Same reference #1 in Jacobson and Masters, Nov 2
(2) Engineering News Record, June 11, 2001 @
http://www.bv.com/bv/news/articles/grid_sols.htm |
|
Response to Jacobson and Masters |
21 November 2001 |
|
|
Joseph F. DeCarolis and David W. Keith Engineering and Public Policy, Carnegie Mellon University
Respond to this E-Letter:
Re: Response to Jacobson and Masters
|
We have enjoyed our dialog about the cost of large-scale wind energy.
We judge that much - perhaps all - of our disagreement stems from
differing assumptions, rather than dispute over the factual content such
as the cost and performance of wind turbines or the cost of long-distance
transmission. With this letter, we aim to make our assumptions explicit
and then respond to Jacobson and Masters' critique of our letter to Science.
We assume the following:
1. Wind energy could realistically effect deep reductions in the
environmental damages (air pollution, CO2) imposed by fossil-based
electric power systems.
2. In response to the CO2-climate problem, we expect that it will be
necessary to make deep reductions (over 50%) in electric sector emissions.
We are interested in estimating the cost of wind if it were to supply a
substantial fraction, on the order of one-fourth, of U.S. demand.
3. If wind is to be exploited at very large scales (hundreds of gigawatts of
output), we anticipate that environmental, aesthetic, and economic
considerations will dictate that the bulk of the wind capacity be located
in the windy regions of the Great Plains.
Below we address the critiques you raised regarding our letter.
1. Hirst’s analysis and intermittency. We were impressed by Hirst’s
analysis, “Interactions of Wind Farms With Bulk-Power Operations and
Markets,”(1). The paper analyzes import of wind energy from the Lake
Benton site in southwestern Minnesota to the PJM grid. The analysis is,
however, not pertinent to our disagreement about the cost of intermittency
because it treats a case where the wind power supply is too small to
significantly influence the power market. The Benton array has a small
capacity (~100 megawatts) and is being imported into a massive grid capable of
supporting a peak load of 52 gigawatts. Hirst addresses this issue by adding a
wind multiplier parameter, but his analysis still only extends to wind
serving less than 10 percent of generation. Hirst’s general conclusion
only supports our intuition: “as the size of the wind farm increases
relative to the control area, the average price it receives for its output
declines.”
2. The economics of backup when wind is baseload. There is an
additional complication not presented in the Hirst paper that is only
relevant when wind is treated as baseload capacity. Although
geographically dispersing turbine arrays can decrease the variance in wind
power output, there will still be times when turbine output is minimal.
Therefore, there must be a significant amount of backup capacity or
storage. But because many of these generating or storage units will be
used infrequently only when the wind doesn’t blow, there use will
be small and the amortized cost will be spread over fewer kilowatt hours of
production, making the incremental cost of backup very expensive. Given
points 1 and 2, we think your suggestion that the cost of intermittency is of
order 0.05˘/kWh is implausible. We think our disagreement here is
completely driven by differing assumptions about wind’s fraction of
electric capacity.
3. Correspondence between wind resources and the existing grid. We do
not dispute your statement that several hundred gigawatts of wind resources exist within
10 miles of existing transmission infrastructure (2). However, we think
that this may not be relevant for three reasons detailed below.
(a). Economic considerations. Exploiting wind resources close to
existing transmission grids is not necessarily the most cost-effective
solution. Because wind turbine output exhibits a cubic dependence on wind
speed, wind power output is very sensitive to location. For instance, it
may be true that installing 10 gigawatts of turbine capacity in the Pembina
Escarpment of North Dakota, a wind class 5 area, and transporting the
electricity to the PJM grid via HVDC lines is roughly equivalent in cost
to simply installing the wind turbines in southwestern Pennsylvania, in
wind classes 3-4 and neglecting transmission costs. For the same reason,
we do not believe it is coincidental that Hirst chose to look at wheeling
wind power from Lake Benton, a wind class 6 site, to the PJM grid.
(b). Transmission considerations. In addition to considering the
location of wind turbines with respect to the existing grid, a
comprehensive assessment of existing transmission and distribution line
capacity of the local grid must be performed, as your reference clearly
indicates (2). We would wager that the existing grid located near the
Pembina Escarpment would not support the hypothesized 10 gigawatts of additional
electric power from new turbine arrays. As such, we still believe that
long-distance HVDC transmission lines would be a critical component of
large-scale wind. Jacobson and Masters say that the cost of 1.5 ˘/kWh “is not supported
by the actual cost of transmission lines,” but they provide no reference to
other estimates of HVDC costs. We can cite many studies that show
amortized HVDC costs to lie in the 1-2 ˘/kWh for these distances.
(c). Aesthetic considerations. Although there are substantial wind
resources near population centers (and the grid), we are skeptical that
these would be developed at large scales. For example, where we live in
western Pennsylvania, there are substantial wind resources located on the mountain
ridges, and in principle these could supply power to the PJM grid.
However, to supply substantial power a developer would need to use almost
all the ridge tops, which we believe would be unacceptable to local
residents. We judge that aesthetic and environmental concerns would push
large-scale wind into the Great Plains.
4. Wind versus coal. We realize that electricity production from coal
results in significant environmental externalities, which must be
addressed. Rather than speculating on the costs of coal externalities, we
assume that coal with carbon capture may present a comparable solution to
wind by minimizing power plant emissions. Such costs will likely raise the
price of coal to the 5-7 ˘/kWh range (3, 4). This is the price wind will
need to compete against. As for the cost of wind, we simply used your
claim of 3-4 ˘/kWh for the amortized capital cost of wind turbines, and
are therefore confused by your statement that “the authors use wind cost
statistics from past experience.” We do not seriously dispute your
estimate of the average cost of wind generation at a given site.
We believe that wind may present an economically viable alternative
to coal with carbon capture, but to assert that, “the cost of wind energy
is now less that of coal” is not accurate. If it were, we would expect to
see wind dominate virtually all new capacity installations (given the 1.5
˘/kWh tax incentive), rather than simply having the fastest relative
growth rate – not an overly impressive statistic for an energy technology
that is cheaper than coal.
We welcome any feedback and would like to continue this dialog.
References and Notes
1. E. Hirst, Interactions of wind farms with bulk-power operations and
markets, http://www.EHirst.com/PDF/WindIntegration.pdf, 2001.
2. M. Shaheen, Wind Energy Issue Brief 9a (October 1997)
(http://www.nationalwind.org/pubs/wes/ibrief09a.htm).
3. E.A. Parson and D.W. Keith Science 1998 November 6; 282: 1053-1054.
4. H. Herzog, The Economics of CO2 Separation and Capture, Technology, 7,
pp. 13-23 (2000). |
|
Re: Re: Wind vs. Coal |
21 November 2001 |
|
|
Alfred Cavallo, Physicist U.S. Department of Energy
Respond to this E-Letter:
Re: Re: Re: Wind vs. Coal
|
I would agree with the letter writers that it is an exaggeration to say
that wind is competitive with coal. I have examined the issues of distance from demand centers and intermittency. My most
recent paper was published in the November issue of JSEE in which I compared storage
costs.
Intermittent wind generated electricity can be transformed to a
constantly available power supply economically by using compressed air
energy storage (CAES) systems. Costs, including transmission and storage
costs, are computed for a realistic system in (1).
Transmission lines are not only costly, but quite difficult to site.
Nobody wants one in their neighborhood. This can be overcome, but it
takes great diplomacy and political will to accomplish.
I do believe that wind energy could supply all of the electricity
needed by the United States at a reasonable price, but it will cost more than market
priced coal, which does not take into account any environmental damage
from coal mining, acid rain, or global warming. People should be prepared
to pay a premium for wind energy, or they should be prepared to penalize
dirty power to reflect its real cost.
There is indeed a boom in wind energy in Europe, but it is not caused
by cheap (relative to natural gas or even imported coal) wind power. Wind
power receives premium payments to reflect its attributes. This same
approach should be used in the United States, and indeed the U.S. Production Tax Credit
program does just this. The program is passed for only a few years at a
time, then allowed to lapse, guaranteeing turmoil in the U.S. industry.
Europe has made a policy decision to support clean power at a
reasonable cost, even if it is more costly than fossil fuel generated
electricity. The United States should do the same.
References and Notes
1. High Capacity Factor Wind Energy Systems, JSEE 117, 137 (May 1995). |
|
Re: Wind vs. Coal |
14 November 2001 |
|
|
Mark Jacobson and Gilbert Masters Terman Engineering Center, Stanford University
Respond to this E-Letter:
Re: Re: Wind vs. Coal
|
We disagree with Golomb's premise and believe that our
conclusions still stand. If wind energy replaces 59% of coal energy,
then wind will supply about 30% of U.S. electricity, whereas 70% of
electricity will still be supplied by other sources. As such, there
is still plenty of backup electricity even if wind energy for a day
hypothetically went to zero, which is not even a remote possibility,
given the consistency of daily U.S.-averaged winds. The issue then
is, what is the intermittency cost (the cost of regulation ancillary
service) of wind. A study on this issue has been performed, and it
shows that such costs are about 0.005 to 0.03 cents per kilowatt hour (kWh), which is less
than 1% of the price of wind energy (1). The cost can be
reduced further simply by using an hour-by-hour persistence forecast
at the given location (1). In addition, the greater the number of
turbines at a given wind farm and the greater the number of wind
farms, the more intermittency of individual turbines cancel each
other out. One can imagine a scenario where winds are slow one day at
one wind farm. These slow wind speeds can be made up for by power
generated at one of several other farms, where wind speeds are
faster. It should also be noted that winds near the coast and
offshore are regular and predictable and subject to less
intermittency than winds away from the coast. Based on the above, we
believe it is incorrect to state that wind cannot replace
conventional power generators. Further, our paper discussed
replacement of coal with wind, but we also believe that new wind
should replace new natural gas, whose emissions enhance acid
deposition, urban smog, human health and mortality, visibility
degradation, and global warming, all of which have real costs. In sum, we believe our
conclusions stand.
References and Notes
1. E. Hirst, Interactions of wind farms with bulk-power operations
and markets, http://www.EHirst.com/PDF/WindIntegration.pdf, 2001.
2. Danish Windturbine Manufacters Assoc. (2001).
http://www.windpower.dk/faqs.htm |
|
Wind vs. Coal |
14 November 2001 |
|
|
Dan S. Golomb, Professor University of Massachusetts, Lowell
Respond to this E-Letter:
Re: Wind vs. Coal
|
Jacobson and Masters (24 Aug., p. 1438) make the case that wind-derived electricity could replace a significant fraction of coal derived
electricity, thereby reducing coal carbon dioxide emissions by up to 59%. The cost of
wind-derived electricity is comparable with that of coal-derived
electricity. There is no doubt that a wind turbine does not emit any carbon dioxide (except that emitted by fossil fuels used to fabricate and construct the
turbine), and does not emit any of the other harmful air pollutants
associated with mining, transport, and combustion of coal. But in balancing
the cost-benefit equation, we should be more judicious. Because wind is
intermittent, back-up power generators must be available. Even in North
Dakota, arguably the windiest state in the United States, winds do not blow all the
time. For example, in Bismarck, North Dakota, winds are calm 5% of the time, and blow
less than 3 m/s 40% of the time (1). (The efficiency of wind turbines
declines precipitously when winds blow less than 3 m/s.) Thus, wind power
cannot replace conventional power generators, but only displace the fuel
that conventional generators would use when the wind generators are in
operation. Many coal fired power plants supply the base load, because they
cannot follow the fluctuating demand during peak hours. Peak power is
mainly supplied by gas or diesel fired generators. An efficient combined
cycle gas fired power plant might emit only half as much carbon dioxide per kilowatt
hour as a coal fired generator, so the savings in carbon dioxide emissions by wind
generators might be much less than Jacobson and Masters calculated.
Typically, the fraction of fuel cost to total production cost of
pulverized coal fired electricity generators is in the 24 to 30% range, and
of natural gas combined cycle generators is in the 48 to 58% range (2). Thus,
it is not correct to compare the total cost of coal versus wind generating
costs, and total carbon dioxide emissions of coal versus wind, but only the fuel cost
and carbon dioxide emissions that wind power displaces when the wind generators
operate.
This is not to say that wind-derived electricity is not worthwhile.
The savings in carbon dioxide and other pollutant emissions are real, as well as the
savings in fuel cost. But the cost-benefit equation must be properly
balanced.
References and Notes
1. Data supplied by J. Enz, State Climatologist, North Dakota State
University.
2. Same as reference 1. in M. Z. Jacobson and G. M. Masters, Science 293,
1438 (2001). |
|
Don't Dismiss the Midwest's Power Needs |
2 November 2001 |
|
|
Dr. Josh Kurutz, Postdoctoral Fellow University of Chicago, Chemistry Department
Respond to this E-Letter:
Re: Don't Dismiss the Midwest's Power Needs
|
In their argument against wind power, DeCarolis and Keith dismiss
this method of power generation in part because the best generation would
come from the Great Plains, "far from demand centers concentrated on the
coasts." Even if transmission costs prohibited transcontinental power
distribution, Denver, Chicago, Minneapolis, Milwaukee, St. Louis,
Indianapolis, Detroit, Des Moines, Topeka, Kansas City, Winnipeg, Calgary,
Saskatoon, Edmonton, and, possibly, Dallas and Houston would benefit
greatly from plains-derived wind power. Even if it cost the same or
slightly more, wind power would allow more polluting resources to be made
available to the coasts. Just because a good energy solution might not
benefit America's coastal cities does not mean it should be ignored. |
|
|